American River Canyon Drive

Natural Gas Pipelines | Folsom, California

Awarded by PG&E in January 2025, this project replaces aging natural gas infrastructure along American River Canyon Drive in Folsom, extending east on River Ridge Way and west on Oak Canyon Way. The scope includes installation of approximately 2,478 linear feet of 4" gas main and 8,466 linear feet of 2" gas main, 119 gas service replacements, 25 gas service transfers, and deactivation of over 10,500 linear feet of existing 1-1/4", 2", and 4" gas main — utilizing both open trenching and horizontal directional drilling.

During the 2025 construction season, crews installed 2,531 linear feet of 4" gas main and 8,408 linear feet of 2" gas main, completed 59 gas service replacements and 21 service transfers, and deactivated 2,376 linear feet of existing main. Remaining work is on track for completion in 2026.